A free general contractor invoice template that actually works like an app: type your job details, pick a style, and download a clean general contractor invoice as PDF, Word or Excel. Prefilled with typical general contractor line items — no account, nothing uploaded, everything stays on your device.

How to write a professional general contractor invoice

General contractors bill progress draws against the contract — typically a schedule of values where each work item has a contract amount and percent complete. Each application bills: (previous % + this period %) × line value + stored materials − retainage (5–10% held until completion). Change orders bill as approved separate lines. The 'Save as approved' button rolls each period's progress forward so the next application starts from current totals.

Typical general contractor line items

Example: App #2 — $150k remodel

Site prep & foundation — 100% complete ($18k line)$0 this period
Framing — 40% this period ($32k × 40%)$12,800.00
Rough plumbing — 60% this period ($22k × 60%)$13,200.00
Materials stored on site$3,400.00
Subtotal$29,400.00
Less retainage (10%)−$2,940.00
Total this application$26,460.00

Compliance & required info for general contractor invoices

Common general contractor invoice mistakes that delay payment

Payment terms & tips for general contractor

Contractors commonly invoice by progress draw (e.g. 30/40/30 against the contract total) and list change orders as separate lines. Check your state's rules on retainage and always reference the contract or job number.

Add your preferred payment methods (Zelle, check, ACH…) so clients can pay without a follow-up call, and always include a PO or job reference when billing a company — accounting teams reject invoices without one.

General Contractor invoice FAQ

What is a schedule of values?

A breakdown of the contract into line items (foundation, framing, roofing…) each with a contract dollar amount. Progress billing charges % complete per line — it's how GCs, owners and lenders all speak the same numbers.

How does progress billing work?

Each pay application bills the work completed that period per line item: (this period %) × line value + materials stored on site − retainage. Approved amounts roll forward into 'previous %' for the next application.

What is retainage in construction?

A percentage (commonly 5–10%) withheld from each payment until project completion — the owner's leverage for punch-list and warranty items. Several states cap it; it's a negative line on the invoice.

How do I bill for change orders?

As separate lines referencing the approved CO number ('CO #4 — added bathroom'). Never fold them into base-contract lines — that's how disputes start.

What is a lien waiver and when do I send one?

A document exchanging lien rights for payment — conditional (with the invoice) and unconditional (after payment clears). Some states mandate statutory forms; link to your state's official version rather than drafting your own.

What is AIA G702/G703 format?

The industry-standard pay application format: G702 = summary (contract sum, completed to date, retainage, amount due); G703 = the line-by-line schedule of values. The actual forms are AIA-copyrighted; this invoice produces an AIA-style equivalent.